Certified Information Systems Auditor (CISA) — Question 335
During the implementation of an upgraded enterprise resource planning (ERP) system, which of the following is the MOST important consideration for a go-live decision?
Answer options
- A. Post-implementation review objectives
- B. Business case
- C. Rollback strategy
- D. Test cases
Correct answer: C
Explanation
The rollback strategy is crucial because it ensures that there is a plan in place to revert to the previous system if the implementation encounters significant issues. While post-implementation objectives, the business case, and test cases are important, they do not directly address the immediate risk management needed during the go-live phase.