Certified Information Systems Auditor (CISA) — Question 296

Which of the following should be used to evaluate an IT development project before an investment is committed?

Answer options

Correct answer: A

Explanation

The correct choice is a Feasibility study, as it helps determine the viability and potential success of a project before any investment is made. Function point analysis is a technique for measuring software size, while rapid application development focuses on quick delivery and iteration, and earned value analysis (EVA) is used for project performance tracking rather than initial evaluation.