Certified Information Systems Auditor (CISA) — Question 296
Which of the following should be used to evaluate an IT development project before an investment is committed?
Answer options
- A. Feasibility study
- B. Function point analysis
- C. Rapid application development
- D. Earned value analysis (EVA)
Correct answer: A
Explanation
The correct choice is a Feasibility study, as it helps determine the viability and potential success of a project before any investment is made. Function point analysis is a technique for measuring software size, while rapid application development focuses on quick delivery and iteration, and earned value analysis (EVA) is used for project performance tracking rather than initial evaluation.