Certified Information Systems Auditor (CISA) — Question 256
Which of the following MOST effectively minimizes downtime during system conversions?
Answer options
- A. Phased approach
- B. Parallel run
- C. Direct cutover
- D. Pilot study
Correct answer: B
Explanation
The Parallel run method allows both the old and new systems to operate simultaneously, which significantly reduces downtime as users can transition smoothly without interruption. In contrast, a Direct cutover can lead to substantial downtime if issues arise, and while a Phased approach and Pilot study can help with implementation, they do not minimize downtime as effectively as a Parallel run.