Certified Information Systems Auditor (CISA) — Question 253
Which of the following methods will BEST reduce the risk associated with the transition to a new system using technologies that are not compatible with the old system?
Answer options
- A. Pilot operation
- B. Parallel changeover
- C. Modular changeover
- D. Phased operation
Correct answer: A
Explanation
The correct answer is A, as a pilot operation allows for testing the new system in a controlled environment before full deployment, thereby minimizing risks. Options B, C, and D increase the complexity and potential for issues during the transition and do not provide the same level of risk mitigation as a pilot operation.