Certified Information Systems Auditor (CISA) — Question 250

When auditing the feasibility study of a system development project, the IS auditor should:

Answer options

Correct answer: C

Explanation

The correct answer is C because reviewing cost-benefit documentation is crucial to ensure that the project's financial justification is sound. Options A, B, and D, while important, do not directly assess the feasibility of the project's financial aspects, which is the primary focus during this stage.