Certified Information Systems Auditor (CISA) — Question 180

An IS auditor is evaluating the progress of a web-based customer service application development project. Which of the following would be MOST helpful for this evaluation?

Answer options

Correct answer: B

Explanation

Critical path analysis reports are essential for understanding the timeline and dependencies of tasks within a project, making them the most useful for evaluating progress. The other options, such as developer status reports and change management logs, provide valuable information but do not offer the same level of insight into the overall project timeline and critical milestones.