Certified Information Systems Auditor (CISA) — Question 1364

Which of the following should an IS auditor be MOST concerned with during a post-implementation review?

Answer options

Correct answer: A

Explanation

The absence of a maintenance plan is critical as it can lead to long-term issues with system reliability and performance. While minor defects, deployment delays, and budget overruns are important, they are less critical compared to the need for ongoing maintenance to ensure the system's success and sustainability.