Certified Information Systems Auditor (CISA) — Question 1330

An IS auditor reviewing a job scheduling tool notices performance and reliability problems. Which of the following is MOST likely affecting the tool?

Answer options

Correct answer: C

Explanation

The correct answer is C because missing maintenance patches and updates can lead to performance and reliability issues in software tools. Options A and B may affect security or staffing but do not directly relate to performance problems. Option D indicates a classification issue, which may affect prioritization but not the immediate functionality of the tool.