Certified Information Systems Auditor (CISA) — Question 1254
During which phase of a system development project should key performance indicators (KPIs) be established?
Answer options
- A. Planning phase
- B. Initiation phase
- C. Execution phase
- D. Closure phase
Correct answer: A
Explanation
The correct answer is A, as the planning phase is when KPIs are established to measure the project's success. In the initiation phase, the project's scope is defined, but no specific metrics are set. The execution phase focuses on implementing the project, while the closure phase deals with finalizing and evaluating the project outcomes, not setting KPIs.