Certified Information Systems Auditor (CISA) — Question 123

During the implementation of an enterprise resource planning (ERP) system, an IS auditor is reviewing the results of user acceptance testing (UAT). The auditor's
PRIMARY focus should be to determine if:

Answer options

Correct answer: C

Explanation

The correct answer is C because the sign-off from the business process owner indicates that the system meets their requirements and is ready for deployment. While options A, B, and D are important, they are secondary to ensuring that the business process owner has officially approved the results of the UAT.