Which of the following is the GREATEST indication of scope creep in the management of a software development project?
Answer options
- A. Several change requests have been authorized by the project steering committee.
- B. Some requirements are untraceable to the approved business case.
- C. Project budget exceeds the allocated cost.
- D. Project delivery has been delayed by several months.
Correct answer: B
Explanation
Option B is correct because untraceable requirements indicate that the project has deviated from its original scope, which is a hallmark of scope creep. The other options may suggest issues with the project, such as budget overruns or delays, but they do not directly point to the scope of the project expanding beyond its authorized limits.