Certified Information Systems Auditor (CISA) — Question 1175
A steering committee established to oversee an organization's digital transformation program is MOST likely to be involved with which of the following activities?
Answer options
- A. Reviewing escalated project issues
- B. Preparing project status reports
- C. Designing interface controls
- D. Documenting requirements
Correct answer: A
Explanation
The correct answer is A because a steering committee typically focuses on high-level oversight and strategic direction, which includes addressing escalated project issues. Options B, C, and D are more operational tasks that would typically be handled by project managers or team members rather than the steering committee.