Certified Information Systems Auditor (CISA) — Question 1088
An organization is establishing a steering committee for the implementation of a new enterprise resource planning (ERP) system that uses Agile project management methodology. What is the MOST important criterion for the makeup of this committee?
Answer options
- A. Agile project management experience
- B. Senior management representation
- C. Ability to meet the time commitment required
- D. ERP implementation experience
Correct answer: B
Explanation
The correct answer is B, as senior management representation is vital for ensuring alignment with organizational goals and securing necessary resources. While Agile experience, time commitment, and ERP experience are beneficial, they do not hold the same level of importance in influencing project success and strategic direction as having senior management involved.