Certified Information Systems Auditor (CISA) — Question 1004
Which of the following BEST enables a benefits realization process for a system development project?
Answer options
- A. Metrics are evaluated immediately after the project has been implemented.
- B. Metrics for the project have been selected before the project begins.
- C. Project budget includes costs to execute the project and costs associated with the solution.
- D. Estimates of business benefits are backed by similar previously completed projects.
Correct answer: B
Explanation
Selecting metrics before the project begins ensures that the project can be measured against predefined criteria, making it easier to assess its success in realizing benefits. Evaluating metrics after implementation may not provide actionable insights, while including solution costs in the budget and backing estimates with past projects are important but do not directly ensure a structured benefits realization process.