Certified Information Systems Auditor (CISA) — Question 1004

Which of the following BEST enables a benefits realization process for a system development project?

Answer options

Correct answer: B

Explanation

Selecting metrics before the project begins ensures that the project can be measured against predefined criteria, making it easier to assess its success in realizing benefits. Evaluating metrics after implementation may not provide actionable insights, while including solution costs in the budget and backing estimates with past projects are important but do not directly ensure a structured benefits realization process.