Certified in the Governance of Enterprise IT (CGEIT) — Question 56
To ensure that the process of developing a business case for IT-enabled investments continually supports benefits realization, the benefits expected from investment programs must be actively managed through:
Answer options
- A. the system development life cycle.
- B. the economic life cycle.
- C. obsolescence planning.
- D. project life cycle.
Correct answer: A
Explanation
The correct answer is A, as the system development life cycle allows for ongoing management and monitoring of benefits throughout the development process. Options B and C do not specifically focus on the continuous management of expected benefits during IT project development, while D refers to project completion rather than the ongoing management of benefits realization.