Certified in the Governance of Enterprise IT (CGEIT) — Question 158
Which of the following BEST indicates that a change management process has been implemented successfully?
Answer options
- A. Degree of control
- B. Outcome measures
- C. Process performance
- D. Maturity levels
Correct answer: B
Explanation
The correct answer, B, refers to outcome measures that assess the effectiveness of the change management process. While options A, C, and D may provide insights into aspects of the process, they do not directly reflect the success of the outcomes achieved through the change management efforts.