An IT steering committee is preparing to review proposals for projects that implement emerging technologies. In anticipation of the review, the committee should
FIRST:
Answer options
- A. require a review of the enterprise risk management framework.
- B. understand how the emerging technologies will influence risk across the enterprise.
- C. determine if the IT staff can support the emerging technologies.
- D. require a capacity plan and framework review for the emerging technologies.
Correct answer: A
Explanation
The correct answer is A because the committee should first ensure that the enterprise risk management framework is adequately reviewed to understand potential risks associated with new technologies. Option B, while important, is secondary to establishing a risk management framework. Options C and D are also relevant but should follow the risk management review.