During which stage of the software development life cycle (SDLC) is it MOST critical to conduct a privacy impact assessment (PIA)?
Answer options
- A. Development
- B. Implementation
- C. Testing
- D. Planning
Correct answer: A
Explanation
The Development stage is crucial for conducting a privacy impact assessment (PIA) because this is when the software's architecture and features are defined, allowing for the identification of potential privacy risks early on. Conducting a PIA at this stage helps ensure that privacy considerations are integrated into the design before implementation or testing occurs, minimizing risks later in the process.