Agile Analysis Certification (AAC) — Question 97
Through ongoing collaboration with stakeholders the team continues to uncover new information. This is leading to changes to the products that are being produced. The team should:
Answer options
- A. Stop all work until stakeholders can decide what they need
- B. Schedule additional review sessions to speed up stake holder decisions
- C. Accept all changes but delay additional solution development work to minimize rework
- D. Continue as is since the process is working
Correct answer: B
Explanation
Option B is correct because scheduling additional review sessions can help clarify stakeholder needs more quickly, facilitating timely decision-making. Option A is incorrect as halting work would lead to delays and inefficiencies. Option C may help in reducing rework, but it doesn't address the urgency of stakeholder decisions. Option D is wrong because while the process may currently be working, it is essential to adapt to new information rather than sticking to the status quo.