Agile Analysis Certification (AAC) — Question 93

The team is very busy working on a top priority initiative. They have delivered many user stories and have many left to complete. However, the components they are delivering are not yet delivering end-to-end business value. How can the team maintain understanding of the big picture without getting lost in the details?

Answer options

Correct answer: C

Explanation

Creating a story map allows the team to visualize the entire user journey and understand how individual user stories fit into the broader context of business value. In contrast, a gantt chart focuses on scheduling, refining the backlog focuses on prioritization without big-picture context, and fully elaborating user stories can lead to unnecessary detail that obscures the overall vision.