Agile Analysis Certification (AAC) — Question 86
When recommending solution options at the Initiative Horizon, the team decides that their goal is to provide decision makers with:
Answer options
- A. The exact cost and timeframe options will take to complete
- B. Just enough information to make an informed and accurate decision
- C. The list of stakeholders that are allowed to have input
- D. Everything known about the resource team doing the delivery
Correct answer: B
Explanation
The correct answer is B because the goal is to provide just enough relevant information to allow decision makers to make informed choices without overwhelming them. Options A, C, and D do not align with this objective as they either provide excessive detail or focus on specific groups rather than the decision-making process.