Agile Analysis Certification (AAC) — Question 79
In a planning workshop the team breaks down the product backlog increment and can assign work to members of the team. This is referred to as:
Answer options
- A. Release planning
- B. Task planning
- C. Resource planning
- D. User story writing
Correct answer: B
Explanation
The correct answer is B, Task planning, as it specifically involves breaking down tasks and assigning them to team members. Release planning refers to broader scheduling of releases, Resource planning focuses on managing resources, and User story writing involves creating user stories rather than assigning tasks.