Agile Analysis Certification (AAC) — Question 75
At the strategy level, a major component of waste can be avoided by ensuring the enterprise:
Answer options
- A. Only begins an initiative when a budget is approved for all work
- B. Has a shared understanding of organizational goals and priorities
- C. Has changes to existing work approved by senior management
- D. Has comprehensive business cases approved by senior management
Correct answer: B
Explanation
The correct answer, B, emphasizes the importance of a unified understanding of goals and priorities to avoid misalignment and waste. Options A, C, and D focus on procedural steps that, while important, do not directly address the foundational understanding necessary to prevent waste at the strategy level.