Agile Analysis Certification (AAC) — Question 68
The team members are discussing the level of effort that different backlog items are likely to require, and how much effort is available for the next sprint. This is an example of the principle:
Answer options
- A. Analyze to determine what is valuable
- B. Understand what is doable
- C. Respect for individuals
- D. Get real using examples
Correct answer: B
Explanation
The correct answer is B because the team is focused on assessing the feasibility of completing tasks within the sprint, which aligns with understanding what can realistically be accomplished. Options A, C, and D are not relevant as they pertain to value assessment, interpersonal respect, and practical examples, rather than evaluating the team's capacity for work.