Agile Analysis Certification (AAC) — Question 51
While working at the initiative level, the team is unsure if they are producing more output than is necessary. After some discussion they decide the following risk mitigation strategy would help:
Answer options
- A. Produce and release an MVP version of the product to your customers
- B. Demo the completed items with key stakeholders as soon as they are ready
- C. Review completed items with management as they are completed
- D. Assess if the need has been met every time a solution component is delivered
Correct answer: A
Explanation
Producing and releasing an MVP allows the team to gather feedback from customers, ensuring they are meeting actual needs rather than overproducing. The other options focus on internal reviews and demos, which do not directly address the concern of excessive output and may delay customer feedback.