Agile Analysis Certification (AAC) — Question 48
The team is working at the Initiative Horizon and receives end-user feedback about the MVP. They determine that the immediate next step is to:
Answer options
- A. Develop internal agreement with a retrospective
- B. Hold workshops to ensure shared understanding
- C. Review stones for cost evaluation
- D. Reassess the priority of planned solution components and features
Correct answer: D
Explanation
The correct answer is D because reassessing the priority of planned components and features allows the team to align their development efforts with the most pressing user needs. The other options, while valuable, do not directly address the need to prioritize changes based on user feedback.