Agile Analysis Certification (AAC) — Question 26
When the product owner determines there has been enough value delivered on the initiative to satisfy the need, then the sponsor’s immediate next step is to:
Answer options
- A. Cancel future work on the initiative to avoid waste
- B. Start work on the list of enhancements to improve the delivered product
- C. Hold individual interviews to collect feedback
- D. Dive deeper into the next delivery cycle’s stories
Correct answer: D
Explanation
The correct answer is D because after confirming that enough value has been delivered, the sponsor should focus on planning for the next delivery cycle to ensure continuous improvement. Options A, B, and C do not align with the immediate next step of preparing for upcoming work, which is essential for maintaining momentum in development.