During a delivery team meeting, some members of the team are confused about the “time” dimension depicted on a story map. After some discussion they conclude it describes:
Answer options
- A. User story implementation order
- B. The project timeline
- C. Sequence of activities a user follows
- D. Time to complete stories
Correct answer: D
Explanation
The correct answer is D because the 'time' dimension on a story map typically relates to the time required to complete the stories. Options A, B, and C represent different concepts that do not accurately reflect the specific meaning of 'time' in this context.