Agile Analysis Certification (AAC) — Question 121
The team is assessing the initiative and have a number of important decisions to make. These decisions provide valuable feedback to consider at the Strategy Horizon where the following can be determined:
Answer options
- A. Measure of progress against the plan
- B. Ability of the delivery team to complete the work
- C. Impact to other ongoing initiatives
- D. Amount of money currently spent
Correct answer: B
Explanation
The correct answer is B because it focuses on the delivery team's ability to finish the work, which is crucial for assessing project feasibility at the Strategy Horizon. The other options, while important, relate to different aspects of project management, such as financial tracking or impacts on other initiatives, rather than the delivery team's capacity.