Agile Analysis Certification (AAC) — Question 117
While developing the initial backlog, the team working at the Initiative Horizon determine they will need to prioritize and sequence solution components:
Answer options
- A. Once only and during release planning
- B. Whenever it is demanded by management
- C. Multiple times throughout the course of an initiative
- D. At the end of each release
Correct answer: C
Explanation
The correct answer is C because prioritizing and sequencing solution components should occur multiple times to adapt to changing requirements and feedback throughout the initiative. Answer A is incorrect as it suggests a one-time event, while B implies prioritization is solely at management's discretion, and D incorrectly states that it should only happen at the end of releases.