Agile Analysis Certification (AAC) — Question 113
When reviewing the initiative, the team has determined that the solution is not delivering the desired outcomes or sufficient value. A viable option to consider is:
Answer options
- A. Release the product
- B. Cancel the initiative
- C. Assign to a new team
- D. Restart the work
Correct answer: B
Explanation
The correct answer is B, as canceling the initiative is appropriate when the solution is not meeting its objectives. Options A and D suggest continuing with the current approach, which is counterproductive if the initiative is not providing value. Option C may introduce new perspectives, but if the project is fundamentally flawed, it may not resolve the underlying issues.