Entry Certificate in Business Analysis (ECBA) — Question 90
Which stakeholder has responsibility to review and approve requirements?
Answer options
- A. Sponsor
- B. Business analyst
- C. Project manager
- D. End user
Correct answer: A
Explanation
The Sponsor is typically the stakeholder who has the authority to review and approve the requirements, ensuring they align with the project's goals. The Business analyst and Project manager play crucial roles in gathering and managing requirements, but they do not have the final approval authority. End users provide input on requirements but do not hold the responsibility for approval.