Entry Certificate in Business Analysis (ECBA) — Question 61
When should prioritization of requirements take place?
Answer options
- A. At the very beginning of an initiative only
- B. After the maintain requirements and trace requirements tasks have been completed
- C. Continually throughout the initiative
- D. After the maintain requirements task has been completed
Correct answer: C
Explanation
The correct answer is C because prioritization should be an ongoing process to adapt to changes and new insights throughout the initiative. Options A, B, and D suggest that prioritization is a one-time event, which does not account for evolving requirements and project dynamics.