Entry Certificate in Business Analysis (ECBA) — Question 6
Which of the following activities are performed during the requirements life cycle management phase?
Answer options
- A. Elicit Requirements
- B. Prioritize Designs
- C. Trace Requirements
- D. Maintain Attributes
Correct answer: C
Explanation
The correct answer is C, as tracing requirements is essential for ensuring that all requirements are accounted for throughout the project. Options A and B refer to different phases of the project lifecycle, focusing on gathering and prioritizing rather than managing existing requirements. Option D, while relevant, does not specifically address the core activities of requirements life cycle management.