Entry Certificate in Business Analysis (ECBA) — Question 30
In addition to schedule, which other factor must be considered when evaluating changes to requirements?
Answer options
- A. Number of customers and end-users affected
- B. Capacity of the requirements management tool
- C. Amount of time needed to create new documents
- D. Agreement by executive board members
Correct answer: A
Explanation
The correct answer, A, is important because the impact on customers and end-users can significantly influence the project's success and acceptance. The other options, while relevant to project management, do not directly relate to the evaluation of how changes to requirements affect stakeholders.