What is a valid reason for prioritization?
Answer options
- A. Requirements which are of significant personal interest to a stakeholder
- B. Effort and resources needed to implement a requirement
- C. Sponsor's wish-list
- D. Development team's advice to implement easy requirements
Correct answer: B
Explanation
The correct answer, B, highlights the importance of considering the effort and resources required for implementing a requirement, which directly impacts project feasibility. The other options are based on subjective interests or preferences that do not align with objective prioritization criteria.