Entry Certificate in Business Analysis (ECBA) — Question 140
Which techniques should be applied to prioritize requirements?
Answer options
- A. Risk Analysis and Management
- B. Decision Modelling and Estimation
- C. Interface Analysis and Interviews
- D. Document Analysis and Vendor Assessment
Correct answer: A
Explanation
Risk Analysis and Management is the correct technique for prioritizing requirements as it evaluates potential risks associated with each requirement, helping to determine their significance. The other options, while useful in different contexts, do not specifically focus on prioritization based on risk assessment.