Certification of Capability in Business Analysis (CCBA) — Question 96
A business analyst is meeting with the customer of the project. The customer tells the business analyst that she can only allow the budget of $575,000 for the project. This budget is best described as what type of constraint?
Answer options
- A. Technical constraint
- B. Verified constraint
- C. Financial constraint
- D. Business constraint
Correct answer: C
Explanation
The correct answer is C, as a budget limit directly relates to financial resources. Options A, B, and D do not accurately capture the nature of the budget constraint, which specifically pertains to financial limitations within the project.