Certification of Capability in Business Analysis (CCBA) — Question 96

A business analyst is meeting with the customer of the project. The customer tells the business analyst that she can only allow the budget of $575,000 for the project. This budget is best described as what type of constraint?

Answer options

Correct answer: C

Explanation

The correct answer is C, as a budget limit directly relates to financial resources. Options A, B, and D do not accurately capture the nature of the budget constraint, which specifically pertains to financial limitations within the project.