Certification of Capability in Business Analysis (CCBA) — Question 80

Which of the following approaches describes the project management approach of refining requirements and project scope?

Answer options

Correct answer: D

Explanation

The correct answer is D, as progressive elaboration involves continuously refining and detailing project requirements and scope as more information becomes available. Options A, B, and C do not specifically focus on the gradual enhancement of requirements; instead, they refer to different management styles or methodologies that may not emphasize iterative refinement.