Certification of Capability in Business Analysis (CCBA) — Question 80
Which of the following approaches describes the project management approach of refining requirements and project scope?
Answer options
- A. Plan-driven
- B. Change-driven
- C. Iterative
- D. Progressive elaboration
Correct answer: D
Explanation
The correct answer is D, as progressive elaboration involves continuously refining and detailing project requirements and scope as more information becomes available. Options A, B, and C do not specifically focus on the gradual enhancement of requirements; instead, they refer to different management styles or methodologies that may not emphasize iterative refinement.