Certification of Capability in Business Analysis (CCBA) — Question 60

Which of the following is an output of the Identify Stakeholders process?

Answer options

Correct answer: B

Explanation

The correct answer is B, the Project charter, which is produced during the Identify Stakeholders process as it outlines the project's purpose and identifies key stakeholders. The other options, such as Scope baseline, Stakeholder register, and Project scope statement, are outputs from different processes within project management and do not directly result from identifying stakeholders.