Certification of Capability in Business Analysis (CCBA) — Question 512
When can changes to requirements occur in a business analysis planning and monitoring assignment?
Answer options
- A. Changes to requirements can occur any time after the project's change control system has been enacted.
- B. Changes to requirements can occur at any time.
- C. Change to requirements can occur any time before the project scope statement is created.
- D. Change to requirements can occur at any time before the key stakeholders approve the identified requirements.
Correct answer: D
Explanation
The correct answer is D because changes to requirements are typically allowed until the key stakeholders have approved them, ensuring that all parties agree on the project direction. Options A and C incorrectly suggest that changes are restricted to after certain documents are created or approvals are in place, which is not accurate. Option B states that changes can occur at any time, which is misleading as approvals are necessary to finalize requirements.