Certification of Capability in Business Analysis (CCBA) — Question 462
A business analyst (BA) is in the process of eliciting requirements. It has been determined that not all requirements can be implemented by the project deadline due to complexity. What must the BA do to ensure maximum benefit for the stakeholders?
Answer options
- A. Ensure users are trained based on requirements
- B. Apply quality control on requirements
- C. Utilize requirements documentation template
- D. Maintain requirements based on priority
Correct answer: D
Explanation
The correct answer is D, as prioritizing requirements allows the BA to focus on delivering the most critical features first, ensuring stakeholders receive the maximum value. Options A, B, and C are important tasks but do not directly address the need to prioritize requirements for timely delivery.