Certification of Capability in Business Analysis (CCBA) — Question 444

A stakeholder has requested an extremely detailed resolution to an issue during current state analysis that may consume about 20% of the estimated project effort. How should the business analyst (BA) handle the situation?

Answer options

Correct answer: B

Explanation

The correct answer is B because escalating to the project manager allows for a reevaluation of priorities and resource allocation without prematurely committing significant effort. Option A is not ideal since additional funding may not be justified, C could lead to inefficient use of resources, and D may downplay the stakeholder's needs without addressing them properly.