The task of prioritizing requirements creates just one output. What is it?
Answer options
- A. Validated requirements
- B. Requirements (prioritized)
- C. Requirements rankings
- D. Requirements assessment
Correct answer: A
Explanation
The correct answer is A, as prioritizing requirements results in validated requirements that have been confirmed to meet the needs of the stakeholders. The other options, while related to the process of handling requirements, do not specifically represent the unique output produced by prioritization.