Certification of Capability in Business Analysis (CCBA) — Question 418

The task of prioritizing requirements creates just one output. What is it?

Answer options

Correct answer: A

Explanation

The correct answer is A, as prioritizing requirements results in validated requirements that have been confirmed to meet the needs of the stakeholders. The other options, while related to the process of handling requirements, do not specifically represent the unique output produced by prioritization.