Certification of Capability in Business Analysis (CCBA) — Question 405

Complete this sentence in regard to the level of abstraction. Requirements need to say _____________ needs to be done, not ________________ to do it.

Answer options

Correct answer: A

Explanation

The correct answer is A because requirements focus on what needs to be completed rather than the specifics of how it will be carried out. The other options incorrectly suggest aspects like timing, responsibility, or quantity, which do not align with the purpose of defining requirements.