Certification of Capability in Business Analysis (CCBA) — Question 4

You have identified a task in your task list that cannot be completed until the inspector for the project signs off on the initial deliverables. The inspector's signoff on the initial deliverables is called what?

Answer options

Correct answer: A, A

Explanation

The correct answer is A, Constraint, because it refers to a limitation that affects the execution of a task. While B, Assumption, represents something accepted as true without proof, C, Dependency, indicates a relationship between tasks, and D, Milestone, marks a significant point in a project timeline, none of these terms accurately describe the inspector's required approval.