Certification of Capability in Business Analysis (CCBA) — Question 394

You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process. You will need all of the following as inputs to the qualitative risk analysis process except for which one?

Answer options

Correct answer: B

Explanation

The correct answer is B, as the stakeholder register is not a necessary input for qualitative risk analysis. The risk management plan, project scope statement, and risk register are all essential documents that provide crucial information for assessing and prioritizing risks.