Certification of Capability in Business Analysis (CCBA) — Question 37
Bradley is working with the business analyst Marsha to prioritize requirements for their organization. Marsha insists that the requirements be ranked on the cost- benefits analysis of the relative value to the organization. What type of prioritization approach does Marsha want to use in this scenario?
Answer options
- A. Likelihood of success
- B. Business value
- C. Urgency
- D. CBR Ratio
Correct answer: D
Explanation
The correct answer is D, CBR Ratio, as it specifically involves evaluating the costs and benefits to determine the relative value of requirements. The other options, while relevant to prioritization, do not directly relate to a cost-benefit analysis framework like the CBR Ratio does.