Certification of Capability in Business Analysis (CCBA) — Question 346

You have 83 project stakeholders from all across your organization. Some of the stakeholders, such as functional management, require weekly communication from you, while other stakeholders, such as the end users, only need quarterly progress updates. Where can you record these communication requirements based on your stakeholder analysis?

Answer options

Correct answer: D

Explanation

The correct answer is D, the Project communications management plan, as it specifically outlines how communication will be handled with different stakeholders. The other options either focus on scheduling, project scope, or reporting structure, which do not adequately address the specific communication needs of stakeholders.