Certification of Capability in Business Analysis (CCBA) — Question 34
When using a change-driven approach, the business analyst may create an initial list of high-level requirements for the initiative. This high-level requirements list is also known as what term?
Answer options
- A. Requirements envisioning
- B. Project scope
- C. Product scope
- D. Requirements foundation
Correct answer: B
Explanation
The correct answer is 'Project scope,' as it refers to the initial high-level requirements that outline what the project aims to achieve. 'Requirements envisioning' pertains to the process of identifying potential requirements, while 'Product scope' focuses on the features and functions of the product itself. 'Requirements foundation' is not a standard term used in this context.